Tuesday, March 3, 2009

Sunday, October 5, 2008

CTE classes rock

I am excited beyond words to see this project finally on the ground. It is gratifying to see students involved in real-world application of their learning. How very cool that Mr. Hunt's students are putting their expertise to work to keep us informed of this project. CTE classes rock:) DSH

Duella Scott-Hull
Director of School Improvement
Coos Bay Public Schools

Monday, September 29, 2008

Near Complete

A few hours later, the pouring of the stem walls is nearly complete.
Posted by Picasa

Concrete in forms

Getting the concrete in the forms is only half the job.
Posted by Picasa

Hang on

You need a lot of help with the hose and the vibrator man needs to follow and vibrate the air pockets out of the concrete.
Posted by Picasa

Concrete hose

Warning, that concrete hose is extremely heavy.
Posted by Picasa

Poured but not finished

Once the step walls are poured they need to be finished with a trowel and anchor bolts need to be set.
Posted by Picasa

Let the pour begin

Pouring the stem walls is a labor intensive project that requires a full crew.
Posted by Picasa

Concrete Pump

A concrete pump is required.
Posted by Picasa

Pour the Stem Walls

The pouring of the stem walls took place on Friday September 26th 2008. This is the second pour of the project.
Posted by Picasa

Thursday, June 12, 2008

more from 6/12/08






Progress at the end of the year 6/12/08

Here We Go!

Its been a while since we have taken some pictures,but we got some pretty good ones today.
The progress carpentry made is great.
Our new Wood Shop is coming along slowly but surely.

Thursday, May 8, 2008

Another squirrel View/ Only this time with rebar

The pictures you're seeing are of forms, that is to say 2 X 10 lumber (which actually measures 1-1/2" X 9-1/2" but that's another story) is used to "form" the concrete into the mold that will eventually become the footing for the walls of the building. Concrete is great stuff but it has a weakness, it can become brittle and fracture under heavy loads. To solve this problem rebar is used to give added strength to the concrete and minimize the effect of cracks. Just like your spine gives strength to your back, rebar adds strength to concrete. Those that work with concrete for a living often remark that it's not a matter of if concrete will crack, it's a matter of when. Naturally when you poor the concrete into the mold (forms) you want the rebar to end up "in" the concrete not just laying on the ground, that's the purpose of the little 2" X 2" cinder blocks you're seeing; they will hold the rebar out of the dirt and in the concrete. Construction workers often refer to concrete as "mud" so you could say that the purpose of the cinder blocks is to keep the rebar out of the dirt and in the mud.

Tuesday, May 6, 2008


A Squirrels view of the footing.

Footing/Batter board from out side corner.

Thursday, May 1, 2008

Ready to go

The foundation is well on it's way.
Posted by Picasa

Day Dirt!

Let the building begin! this photo was taken on 5-1-08. The dirt work is done and carpenters have arrived to set forms.
Posted by Picasa